Jewelry showcase installation goes wrong most often not because of bad cabinets, but because nobody agreed who does what on site. The electrical contractor arrives before the cases, the store owner assumes the supplier will level and anchor, and the freight team leaves 900 kg of glass in the wrong corner of an unsecured retail floor. The fix is simple and unglamorous: split the work into three clear packages — supplier, installation contractor and store owner — and put each responsibility in writing before the purchase order is signed. Here is how that split usually works for retail and museum projects, including the numbers worth checking.
What the showcase supplier is responsible for
The supplier owns the product: design, fabrication and factory-level quality control. For a typical jewelry store package of 15 to 25 cases, this includes producing shop drawings and a lighting and power layout within 5 to 10 working days of deposit, then building to tolerances of about ±1 mm on glass-to-frame joints and ±2 mm on overall dimensions. The supplier should test all LED runs (usually 24V or 12V systems, 3000K to 4000K, CRI 90+) before crating, protect glass with foam and edge guards, and provide a packing list matched to the floor plan so cases can be placed room by room.
The supplier is also responsible for documentation: assembly instructions, anchor specifications, load ratings, electrical schematics and warranty terms (glass and hardware are often covered differently — 12 months on lighting components and 24 months on the frame is common). What the supplier does not do by default is site labor. Unless a turnkey installation is contracted, do not assume the supplier’s team will drill anchors, run conduit, or lift cases up three floors. Libafang, like most Guangzhou manufacturers exporting to 30+ countries, quotes ex-works or FOB as standard, with installation supervision or full installation as a separately priced option.
What the installation contractor is responsible for
The contractor converts a delivered cabinet into a fixed, safe, powered fixture. Their scope typically covers site measurement and verification before delivery, unloading and internal distribution, assembly (many cases ship in base, glass and lighting sections), leveling to within 1–2 mm across a run, mechanical anchoring, electrical connection to the store’s distribution board, and disposal of crating. On a normal retail fit-out, two to three installers can position and level 10 to 15 standard cases in a day; glass-heavy tower or museum-grade cases take longer, often one to two hours each.
Anchor and floor questions belong here. A loaded jewelry showcase can weigh 150–400 kg, and tall glass towers should be anchored against tipping. The contractor confirms the substrate — concrete, raised access floor, or timber — and uses the supplier’s specified anchors. If a floor cannot take the point loads, that is a contractor finding to be raised before installation day, not after.
What the store owner is responsible for
The store owner carries site readiness, access and utilities. Concretely, that means: delivering a lockable, weather-tight space with finished floors and cleared routes at least 24 to 48 hours before installation; confirming door and corridor widths against the largest crate (a 2.4 m glass tower will not pass a 900 mm service door); ensuring 220V/110V power, as specified, is live at the case positions or at a clearly marked distribution point; and arranging building permission, lift booking, parking and any after-hours access. Owners also approve shop drawings and sign off a punch list at handover. Delays here are the single most common cause of added installation days, and most contracts bill standby time by the day.
Who does what: a practical checklist
Use this split as a starting template, then adjust per contract. Ambiguity is the enemy; every line should have one owner.
- Shop drawings and electrical layout — supplier produces; owner approves; contractor verifies against site.
- Case fabrication, factory testing and packing — supplier.
- Freight, customs clearance and delivery to site — per Incoterms; usually owner or their freight forwarder from FOB port onward.
- Unloading, internal distribution and assembly — contractor (or supplier if turnkey).
- Leveling, anchoring and electrical hook-up — contractor, to the supplier’s specifications.
- Site access, power availability, lift and permits — store owner.
- Final cleaning, function test of every light and lock, and punch list — contractor performs; owner signs off.
- Warranty response and spare parts — supplier; routine lamp and driver replacement — owner’s maintenance budget.
Where responsibility usually blurs — and how to fix it
Four gray areas cause most disputes. First, damage in transit: clarify who insures the shipment and from which point. Second, electrical termination: some suppliers ship cases with a plug, others with bare leads for hard-wiring; the contractor needs to know which before arriving. Third, glass handling: if the contractor chips a shelf during installation, that is typically their liability, which is why installation insurance matters. Fourth, anchor responsibility: assign it explicitly to the contractor, with the supplier providing anchor type and load data.
The easiest protection is a one-page responsibility matrix attached to the contract, plus a pre-installation call 10 to 14 days before delivery covering dates, crew size, power, access and the crate list. Consider retaining 5 to 10 percent of the installation value until punch-list items are closed. This is standard practice and keeps handover orderly.
Plan the split before you place the order
Decide your installation model — supply-only, supplier supervision, or turnkey — while you are still specifying the cases, because it changes packing, electrical terminations and documentation. If you are planning a jewelry store, watch boutique or museum vitrine project, Libafang can supply a project-specific responsibility matrix with your drawings and quote. Request a free design and quote with your floor plan and case schedule, and we will confirm exactly what we handle, what your contractor handles, and what stays with you.